Tuipui

General Overview: The project included construction of 85m span bridge over River Tuipui in Mizoram State. The substructure had already been constructed by the department. The superstructure arrangement consisted of three PSC spans (two 20m T-Beam and one box girder type). The bridge site was located at km 130.24 on Seiling Champai Road under project Pushpak in Mizoram State. The project was completed one month in advance.

 

Contract Amount: Rs. 3,78,00,000/-

Associated Client: Border Roads Organization

Date of Completion: 23 Nov, 2012