B III / Bakchu Khola

General Overview: The project included design and construction of 120 m long bridge. The superstructure is balanced cantilever PSC continuous type and substructure consists of abutments on open foundation and two piers on well foundation. The bridge site is located at km 23.45 on road Gangtok-Chungthang under project Swastik in Sikkim state.

 

Contract Amount: Rs. 9,90,00,000/-

Associated Client: Border Roads Organization

Design Consultant for the Project: Engineering Project Consultants-Thane

Date of Completion:  24 Mar, 2016